GessoDigital Project Status Log
Date: 05/16/2001
Actual Hours
Estimated Hours
Resource
19-Mar
26-Mar
2-Apr
9-Apr
16-Apr
23-Apr
30-Apr
7-May
14-May
Totals
Calender Hours
40
40
40
32
40
40
40
40
40
352
Bala
16
40
40
27
44
44.5
47
44
40
342.5
Susan
0
0
23
23.5
40
39.5
32
35.75
40
233.75
Girish
1
12
3
3.5
3.5
9
6
Not submitted
4
42
Richard
0
2
9.25
13.25
23.5
3.5
4
30
8
93.5
Pamela
0
0
0
3
0
0
0
0
0
3
Misa
0
0
0
0
0
0
0
0
0
0
Total Hours
17
54
75.25
70.25
111
96.5
89
109.75
92
714.75
Grand Total:
714.75
Resource Allocation To Date
Resource
Hours-to-
Hours
date
Remaining
Bala
342.5
40
Susan
233.75
40
Girish
42
4
Richard
93.5
8
Misa
0
0
Total Hours
714.75
92
Risk Factors
UI from Gesso is late which may cause a delay in development. There may also be some changes to the template which may cause Tgix to redo
As Project Plan is aggressive, depending on amount and complexity of bugs found within QA cycle can add more time to project.
Needed to compile Tomcat for Production environment as we were unaware that the hosting facility did not support this s/w.
Bridging Apache and Tomcat created unexpected problems in jsp component. (Learning curve for Tgix resources)
Proprietary and Confidential Document
© Copyright 2001 Thaumaturgix, Inc.
1 of 1
19 W 44th Street, 18th floor, New York, NY 10036
5/16/2001 1:07 PM
(v) 212-918-5000 - (f) 212-918-5001
Gesso_Project_Status Project_Summary